6.27.19 Campus Update

Good afternoon.

From July 1 through July 31, exterior wall repairs will be taking place on the east facing facade of Brown Hall which will include closing a portion of the ADA ramp. During this time ADA access to Admissions and Financial Aid will be through the passenger elevator in the main front entrance of Brown Hall. In addition, limited access is available from the ground floor parking lot passenger elevator on the ground floor of Brown Hall. ADA parking will be available directly in front of the main entrances to Highsmith Student Union and Brown Hall. 

Additional details will be available next week regarding further sidewalk closures in this area. 

If you have any questions or concerns please contact Campus Operations at 251-6564.

David Todd
Associate Vice Chancellor Campus Operations