9.19.17 Campus Update

City of Asheville Resurfacing N. Edgewood Tue Sept 19 - Fri Sept 29

We received the following update from the City of Asheville regarding the ongoing resurfacing project:

The Resurfacing contractor will be milling, doing utility adjustments and paving on N. Edgewood between Barnard and Hyannis from today [Sept. 19] until the end of next week.

One lane will be closed at a time to allow traffic to move in the opposite lane.

After that we will be moving to N. Edgewood from Kimberly to Merrimon Ave.

Sidewalk Closure Wed Sept 20 - Fri Sept 22

Beginning Wednesday, Sept 20 through Friday, Sept 22 we will run IT data lines under a section of sidewalk for the new housing site.  This work requires closure of a section of sidewalk and (7) parking spaces on the south side of University Heights as indicated on the attached map.

Please use the sidewalk on the north side of University Heights (Rhoades / Robinson side) during this time.  Traffic on University Heights should not be impacted by this work.

If you have questions regarding construction, please email campusconstruction@unca.edu or contact Campus Operations at 828.251.6564.  For updates and more details, visit https://facilities.unca.edu/construction

David Todd
Associate Vice Chancellor of Campus Operations